Neoen’s Collie Battery Stage 1 begins operating in Western Australia
The 219 MW / 877 MWh battery, the largest in Western Australia to date, will be instrumental in supporting electricity reliability as the State transitions to renewable energy.
neoen.com

Neoen has taken less than 18 months to build and start operating its 219 MW / 877 MWh Collie Battery Stage 1. The battery storage facility is located near the town of Collie, on the country of the Wilman people of the Bibbulmun nation, in the South West region of Western Australia (WA) and is the largest battery in WA to date. It is the first Neoen asset to connect into South-West Interconnected System (SWIS) and, in collaboration with Tesla, UGL and network service provider Western Power, it was delivered ahead of schedule.
On 1st October, Collie Battery Stage 1 began delivering its 197 MW / 4-hour grid capacity service to the Australian Energy Market Operator (AEMO). The contract, called ‘Non-Co-optimised Essential System Services’ (NCESS) runs for a period of two years. The battery provides 197 MW of storage capacity for 4 hours, charging during the day and then discharging across the evening peak. This service is designed to address the risks AEMO identified relating to the phased retirement of WA Government owned coal-fired power plants and increasingly high penetration of rooftop solar in Western Australia.
The battery is Neoen’s first major project in WA and its first 4-hour long duration battery globally. Collie Battery Stage 2 (341 MW / 1,363 MWh), which is currently under construction, was awarded a similar 300 MW / 4-hour NCESS contract by AEMO in April 2024. Altogether, the Collie Battery (560 MW / 2,240 MWh) will have the ability to charge and discharge 20% of average demand in the SWIS. It illustrates Neoen’s strategy of deepening its investment in storage through extended duration, enabling it to unlock greater value. Long duration storage is increasingly needed as electricity networks transition to higher penetrations of renewable energy.
Neoen is Australia’s leading developer, owner and operator of batteries and its storage portfolio in operation or under construction in the country currently sits at 1,925 MW / 4,709 MWh. This includes the 300 MW / 450 MWh Victorian Big Battery in Geelong and the flagship 150 MW / 193.5 MWh Hornsdale Power Reserve in South Australia, both in operation, as well as several batteries currently under construction: 238.5 MW / 477 MWh Blyth Battery in South Australia, two stages of Western Downs Battery in Queensland (both sized at 270 MW / 540 MWh) and the 100 MW / 200 MWh Capital Battery in the Australian Capital Territory.